PPS
Plan and output by working day. A working day starts at 08:00. Today is left out because it is still open. Hourly output stays on UPH.
89.2%
Achieved · 7 days
85.2%
Achieved · 3 months
85.0%
Achieved · 6 months
85.0%
Achieved · since Mar 2026
332,958
Plan (EA)
7 days · 16–22 Nov
297,118
Actual (EA)
7 days · 16–22 Nov
89.2%
Achieved
7 days · 16–22 Nov
−35,840
Gap (EA)
7 days · 16–22 Nov
Output, 16–22 Nov
Plan Actual
Achieved, 16–22 Nov
Achieved
Output by line, 16–22 Nov
Plan Actual
Lines run from the lowest achieved rate to the highest. A line with no plan and no output is omitted.
Line 7
83.0%
Line 3
83.4%
Line 1
84.7%
Line 6
88.9%
Line 8
90.3%
Line 2
90.5%
Line 9
91.2%
Line 5
94.8%
Line LTE
97.5%
| Line |
Plan (EA) |
Actual (EA) |
Achieved |
Gap (EA) |
| Line 7 |
32,081 |
26,629 |
83.0% |
−5,452 |
| Line 3 |
32,332 |
26,950 |
83.4% |
−5,382 |
| Line 1 |
48,935 |
41,458 |
84.7% |
−7,477 |
| Line 6 |
29,326 |
26,060 |
88.9% |
−3,266 |
| Line 8 |
57,980 |
52,368 |
90.3% |
−5,612 |
| Line 2 |
36,942 |
33,437 |
90.5% |
−3,505 |
| Line 9 |
28,828 |
26,295 |
91.2% |
−2,533 |
| Line 5 |
35,708 |
33,857 |
94.8% |
−1,851 |
| Line LTE |
30,826 |
30,064 |
97.5% |
−762 |